Building the Bioreactor

 
 
Purcell+Park-bioreactor+layout.jpg

Concept Layout

Identify an area of high nitrogen input to the watershed. The bioreactor relies on natural flow patterns and must be positioned accordingly.

20140301_Trade-151_0124-copy.jpg

Excavate the Trench

Dig a trench of the appropriate dimensions to handle the flow volume expected in each location. Flow volume is related to the normal source flow volume from agricultural run-off or tributary streams sources.

Covering the wood chips with  filter fabric before covering in dirt.JPG

Layer Wood Chips, Filter Fabric, and Dirt

The materials layered in the bioreactor promote the growth of beneficial microbes and provide physical filtration and water retention. Structuring these materials supports maximum efficiency of the natural nitrogen removal process.